Why I'm happy my off plan villas in Abu Dhabi are delayed

By Jake Nazer

Written . This is Jake Nazer's own view and was true on that date. For the latest facts see the Nawayef guide.

Posted 15 August 2026.

Why I'm happy my off plan villas in Abu Dhabi are delayed.

I own 4 off plan villas in Hudayriyat. Two on East Hill have delays and one in Al Naseem is on time. I am happy two have delays.

In Abu Dhabi, off plan regulations mean the developer has to complete the construction milestone in the SPA before they can charge you that payment. If the work isn't done, the payment date moves until it is.

I have paid 15% towards my villas on East Hill and my villa in Al Naseem. My payment schedule for Nawayef East Hill says 50% of the structural works needs to be completed by June 2026 before my next 5% is owed. It isn't, so my next payment has now moved until it is, in 2027. In Al Naseem I owe 10% at the end of September if 100% of the structural works are done, and from the construction update video Modon released yesterday you can see they are on time, so I will have to pay that one.

Modon have added three months to the East Hill handover. As an investor, construction delays happen, but as demand on the island increases and values increase with it, I benefit from the price rising with no more capital invested, which is a higher return on the capital.

In Dubai the regulations are different. Your money sits in escrow and the developer draws it out in stages as they build, so it's protected. But payments are rarely linked to construction progress and it isn't mandatory, so what you owe isn't tied to the build. The date comes round and you pay either way. That's how you get projects 50% paid with 10% of the work done, and that makes resale harder and suppresses values.